Deformation Mechanism and Crack Cause Analysis of the Left Abutment Slope of Yangfanggou Hydropower Station

文献类型:期刊论文

作者Bing,PAN3,4; Jing,HOU4; Jianjun,XU4; Liuke,HUANG1,2; Weijiang,CHU3,4; Xiangming,GE3
刊名IOP Conference Series: Earth and Environmental Science
出版日期2021-10-01
卷号861期号:7
关键词Yangfanggou Hydropower Station Rock Slope Deformation and Failure Mode Crack Cause Stability Analysis
ISSN号1755-1307
DOI10.1088/1755-1315/861/7/072069
英文摘要Abstract The geological conditions of the left abutment slope of Yangfanggou Hydropower Station are complex, and the unloading effect in the rock mass developing with slope-oriented steep-gentle-dipped fractures is strong. During the excavation of slope, the deformation and cracking response in rock mass on the upstream side of the arch dam foundation have been found successively, the stability of slope and personnel safety has been significantly influenced. Based on engineering geological survey and monitoring data analysis, a discrete element simulation model is built for deformation mechanism and crack cause analysis of the left abutment slope. The calculation results show that: the fault f27 and slope-oriented structural plane with gentle dip are the main factors that influence the deformation response during excavating the slope. During the excavation of the slope above E.L.2000m, f27 has an obvious influence on the local stress at the foot of the slope. The stress will be concentrated in the upper part of f27 firstly and then unloading and relaxed under the combined action of the slope-oriented structural plane. The shear deformation happens along with the fault f27, and the subsidence of its hanging wall caused the crack of the rock mass. The slope stability will be significantly reduced with f27 exposed on the excavation face, there is a large risk of slip and instability. Pre-stressed anchor cables are used to stablish the foot and strengthen the slope half, which can effectively improve the stability of the slope and control the shear deformation of f27. After the pre-stressed anchor cables are applied, the safety factor of the slope is increased from 0.98 to 1.20, and the monitoring data show that the deformation is controlled successfully.
语种英语
WOS记录号IOP:EES_861_7_072069
出版者IOP Publishing
源URL[http://119.78.100.198/handle/2S6PX9GI/28470]  
专题中科院武汉岩土力学所
作者单位1.State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, Wuhan, 430071, China
2.Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China
3.HydroChina ITASCA R and D Center, Hangzhou 311122, China
4.Power China Huadong Engineering Corporation Limited, Hangzhou 311122, China
推荐引用方式
GB/T 7714
Bing,PAN,Jing,HOU,Jianjun,XU,et al. Deformation Mechanism and Crack Cause Analysis of the Left Abutment Slope of Yangfanggou Hydropower Station[J]. IOP Conference Series: Earth and Environmental Science,2021,861(7).
APA Bing,PAN,Jing,HOU,Jianjun,XU,Liuke,HUANG,Weijiang,CHU,&Xiangming,GE.(2021).Deformation Mechanism and Crack Cause Analysis of the Left Abutment Slope of Yangfanggou Hydropower Station.IOP Conference Series: Earth and Environmental Science,861(7).
MLA Bing,PAN,et al."Deformation Mechanism and Crack Cause Analysis of the Left Abutment Slope of Yangfanggou Hydropower Station".IOP Conference Series: Earth and Environmental Science 861.7(2021).

入库方式: OAI收割

来源:武汉岩土力学研究所

浏览0
下载0
收藏0
其他版本

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。