Optimization of Construction Program Schedule Plans Based on Multi-Objective Optimization Theory

文献类型:期刊论文

作者Liu, Yibiao; Cheng, Hongqun; Liu, Chenchen
刊名IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING
出版日期2022-12-01
卷号46期号:6页码:4763
关键词Construction program Schedule plan Improved adaptive NSGA-II Multi-objective optimization Duration optimization Resource leveling
ISSN号2228-6160
英文摘要Multiple sub-projects in a construction program (CP) generally involve overlapping construction times and serious resource conflicts, and the decision-making environment is complex and changeable. Optimizing the schedule plan is an effective way to ensure that the mandatory CP duration is met. Based on multi-objective optimization theory, an optimization model for CP schedule plans is established to achieve CP duration optimization and resource leveling. An improved adaptive NSGA-II algorithm (IANSGA-II) is proposed to enhance the convergence, uniformity, and spread of the optimization results. An optimization process for CP schedule plans is presented based on the proposed model and algorithm. A case study of a geological disaster treatment program is conducted, and an optimized schedule plan set containing three schedule plans is obtained based on the proposed model and algorithm. The case study shows that the proposed optimization model and algorithm are reasonable and adaptive. Compared with the results of the standard NSGA-II and adaptive NSGA-II (ANSGA-II), the Pareto solutions obtained by the IANSGA-II dominate up to 75.6% of the solutions of the ANSGA-II and 91.8% of the solutions of the NSGA-II. This proves that the uniformity and spread of the Pareto solutions obtained by the IANSGA-II are better than those of the other two algorithms. In addition, a metric that can characterize convergence shows that the IANSGA-II has the best convergence. Two theoretical cases show that the proposed algorithm will also work in higher-dimensional search spaces. Optimizing the schedule plan of CPs based on the proposed process will provide decision-makers with more schedule plans to adapt to different decision-making environments.
学科主题Engineering
语种英语
WOS记录号WOS:000778615300002
出版者SPRINGER INT PUBL AG
源URL[http://119.78.100.198/handle/2S6PX9GI/35164]  
专题中科院武汉岩土力学所
作者单位1.Wuhan University
2.Chinese Academy of Sciences; Wuhan Institute of Rock & Soil Mechanics, CAS;
3.Chinese Academy of Sciences; University of Chinese Academy of Sciences, CAS;
推荐引用方式
GB/T 7714
Liu, Yibiao,Cheng, Hongqun,Liu, Chenchen. Optimization of Construction Program Schedule Plans Based on Multi-Objective Optimization Theory[J]. IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING,2022,46(6):4763.
APA Liu, Yibiao,Cheng, Hongqun,&Liu, Chenchen.(2022).Optimization of Construction Program Schedule Plans Based on Multi-Objective Optimization Theory.IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING,46(6),4763.
MLA Liu, Yibiao,et al."Optimization of Construction Program Schedule Plans Based on Multi-Objective Optimization Theory".IRANIAN JOURNAL OF SCIENCE AND TECHNOLOGY-TRANSACTIONS OF CIVIL ENGINEERING 46.6(2022):4763.

入库方式: OAI收割

来源:武汉岩土力学研究所

浏览0
下载0
收藏0
其他版本

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。