Optimization of Rockburst Risk Control Measures for Deeply Buried TBM Tunnels: A Case Study

文献类型:期刊论文

作者Li, Pengxiang1,3; Zhao, Jinshuai4; Bu, Wankui1; Niu, Wenjing2; Liu, Pinpin1; Sun, Minghong1
刊名BUILDINGS
出版日期2023-06-01
卷号13期号:6页码:-
关键词rockburst microseismic monitoring TBM tunnel rockburst control measures
英文摘要Choosing reasonable control measures for different intensity rockburst risks not only effectively prevents and mitigates rockburst risks but also reduces time and engineering investment costs. Due to the limitations of the tunnel boring machine's structure and working conditions, tunnels excavated by TBMs are highly susceptible to rockbursts. What is even worse is that there are very few measures to control the rockburst risk in these tunnels. Implementing reasonable control measures from the limited mitigation measures to control and mitigate rockburst in TBM tunnels is an urgent problem that warrants a solution. In this paper, a large number of on-site rockburst risk control cases and a large amount of MS monitoring data (the total mileage of MS monitoring is approximately 7 km, lasting for 482 days) are used to derive a reasonable scheme to control the rockburst risk of different intensities in twin TBM tunnels. First, the rockburst early warning effect of the two headrace tunnels of the Neelum-Jhelum hydropower station based on microseismic monitoring is analyzed. Second, based on highly accurate rockburst warning results, 94 rockburst risk control cases are applied to analyze the control effect of different control measures at different intensities of rockburst risk. Then, by combining factors such as the time cost and expense cost of different control measures, more reasonable control measures for different intensity rockburst risks are proposed: for slight rockburst risk, normal excavation is preferred; for moderate rockburst risk, horizontal destress boreholes are preferred; and for intense rockburst risk, a combination of measures of shortening daily advance and horizontal destress boreholes is preferred. The research results can provide a reference for other TBM excavation projects to carry out rockburst risk prevention and mitigation.
学科主题Construction & Building Technology ; Engineering
语种英语
WOS记录号WOS:001017055500001
出版者MDPI
源URL[http://119.78.100.198/handle/2S6PX9GI/35416]  
专题中科院武汉岩土力学所
作者单位1.Institute of Underground Space for Stability and Support of Surrounding Rock, Heze University, Heze 274015, China; lipengxiang@hezeu.edu.cn (P.L.); bwk239@126.com (W.B.); liupinpin@hezeu.edu.cn (P.L.); minghongsunnn@outlook.com (M.S.)
2.School of Resources, Environment and Materials, Guangxi University, Nanning 530004, China;
3.State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, Wuhan 430071, China
4.Faculty of Civil Engineering and Mechanics, Jiangsu University, Zhenjiang 212013, China
推荐引用方式
GB/T 7714
Li, Pengxiang,Zhao, Jinshuai,Bu, Wankui,et al. Optimization of Rockburst Risk Control Measures for Deeply Buried TBM Tunnels: A Case Study[J]. BUILDINGS,2023,13(6):-.
APA Li, Pengxiang,Zhao, Jinshuai,Bu, Wankui,Niu, Wenjing,Liu, Pinpin,&Sun, Minghong.(2023).Optimization of Rockburst Risk Control Measures for Deeply Buried TBM Tunnels: A Case Study.BUILDINGS,13(6),-.
MLA Li, Pengxiang,et al."Optimization of Rockburst Risk Control Measures for Deeply Buried TBM Tunnels: A Case Study".BUILDINGS 13.6(2023):-.

入库方式: OAI收割

来源:武汉岩土力学研究所

浏览0
下载0
收藏0
其他版本

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。